Swimming Pool - In-Ground
|
||
Pool Frame - Page F3
|
||
|
Think Summer
|
We continue now with the final steps for exterior Frame Anchors. Frame Anchor Completion After the frame is set and the anchors are in place, a cement truck arrives and they pour cement to a height of about 4" all the way around the pool. They call this a collar. As you can see, the cement is pushed against the wall and covers bottom of each anchor.
The cement will set, holding the pool frame in place and locking the anchors in place. The anchors all have a second function, besides holding the pool frame in place. They are also used to support the cement deck that will surround the pool. That is it for the framing day. The next construction day is the floor.
Below is an overview of the times it will take to complete all the steps discussed on this page. Realistically, they will not happen one day after the next.
3rd Day - Frame Construction Time: 1
Day
|
|
| Next Step - Pool Floor | ||
| Pool
Overview - Overview of this site and project Pool Placement - Where to locate the pool and related issues Pool Site - The start of your pool - digging Pool Frame - Constructing the pool frame (the walls): 3 pages F1 F2 F3 Pool Floor - Constructing the pool floor Pool Liner - Installing the pool liner Pool Start-Up - Getting the pool ready for use Pool Shopping - Tips on how to shop for a pool, lowering your costs & frustrations. |
||
|
© 2005 How To Build It |
||
| Need to find something - use this Google link - it will open a new window. | ||